Wembley Central

Client :- Rok Plc

Project Value :-  £ 6 200 000

Duration :- 44 Weeks

Status :- Completed

S.R.McHugh Ltd carried out the enabling works before the main contractor arrived on site, including a high specification office and welfare facilities  fitout within the existing building.

Once the Main  Contractor was on site, S.R. McHugh Ltd provided them with a Front of House Team,  Project Manager and Finishing Foreman to ensure that the Refurbishment works were carried out to specification and on time.

A logistics and waste management team was also provided to manage the delivery and distribution of materials via the one point of access on this particular site.

This entry was posted in Projects. Bookmark the permalink.